MUGUSU GRAVITY FLOW SCHEME KICKS-OFF AGAIN


Stakeholders from Mugusu sub county who included among others the chairperson LC111, Speaker to council, sub county chief, community development officer, District water officer and Rweco members(IWDP and RIC-NET) on 3rd June 2010 organized a joint monitoring visit to the source of Mugusu gravity flow scheme.

The purpose of this visit was to establish how far the work had reached, the size of the source, the quality of the water, the workmanship at the source and quality of the pipes bee used as the scheme kicks-off again.

This scheme was started in 2008 but was not completed due to delay in release of funds by UNICEF for the pipes and the rest of the hard ware.
During the visit to source the stakeholders observed the following:
1. The source was already blocked by sand, thus a need to overhaul it
2. One the pipe at the source was not bring in water.
3. Pipes in the hilly places were left on the open thus exposing them to landslides.
4. The Cementatation tank near the source was already leaking and needed support.
5. Connectors at the source needed repair.
6. The source attendant was not facilitated to over see the source.
7. Community members who were involved in the digging of the trench for the laying of the pipes still demand their payment.
8. Communities were not sensitized on hygiene and means of maintaining of the gravity flow scheme.

The team thus recommended the following:
1. Train two scheme attendants already identified and the sub county should allocate funds to facilitate these people.
2. Cementatation tank should be repaired since it was leaking.
3. The contractor should be advised to make payment for those who laid the pipes.
4. District engineer should make an assessment of how many tap stands that can be on this scheme before illegal connectors start connecting their homes.
5. Sub county leaders should sensitize the community on hygiene and maintenance of the scheme.
By Timothy Balikenga